Surface Preparation
All surfaces to be in contact with Five Star DP Epoxy Grout shall be free of oil, grease, laitance and other contaminants. Concrete must be clean, sound, dry and roughened to ensure a good bond. An SSPC-SP6 commercial finish on all metal surfaces will optimize bond development to steel.
Formwork
Construct formwork using rigid, non-absorbent materials that are securely anchored, liquid-tight, and strong enough to resist the forces during grout placement. A clearance of 1 to 2 inches (25-50 mm) is recommended between the formwork and baseplate. If no bond is desired in certain areas, treat them with paste wax or polyethylene. Depending on the pour dimensions, isolation joints may be required. For further information, contact Five Star Products’ Engineering and Technical Service Center.
Mixing
For best results, condition all components between 70°F and 80°F (21°C to 27°C) before use. Begin by pouring Component B (hardener) into Component A (resin) and mix thoroughly to avoid air entrapment. Transfer the mixture into a mortar mixer, then slowly add Component C (aggregate), mixing until the aggregate is completely wet. Typically, 4 to 5 bags of aggregate are used, with 4 bags providing better flow. In certain situations, the aggregate may be reduced to 3½ bags for clearances of 1 inch or less. Working time is approximately 90 minutes (60 minutes for High Flow) at 70°F (21°C).
Methods of Placement
Five Star DP Epoxy Grout is typically poured into place. Grouting should be done from one side to the other, maintaining continuous contact with the baseplate. For clearances greater than 18 inches (457 mm) or volumes exceeding 100 cubic feet (2.8 cubic meters), contact Five Star Products for guidance. Use of a headbox is highly recommended for optimal results.
Post-Placement Procedures
Final finishing ensures the grout is flush with the bottom edge of the baseplate. For exposed surfaces, use a solvent-wiped trowel just before the material becomes unworkable. In-service operations can begin once the minimum required grout strength and modulus are achieved.
Clean Up
Clean all tools and equipment with a water and detergent solution before the material hardens. For hardened material, a suitable solvent will be required, with sand acting as an abrasive if necessary.